Concrete ingredients, PERT/CPM network analysis and inventory (EOQ) — the materials and project-planning scorers in GATE CE.

PART 1

Topic Breakdown & Traps

The Engineering Principle

Construction management plans time, cost and resources. A CPM network finds the critical path — the longest chain of activities with zero float that fixes the project duration. PERT treats activity times as uncertain, using a weighted expected time . Inventory is optimised by the Economic Order Quantity that balances ordering and holding costs.

The Core Formula Matrix

PERT expected time:

PERT variance:

Total float: (zero on the critical path)

Economic Order Quantity:

The ‘IIT Traps’

  • Critical path = longest path, not shortest. It has zero total float and governs project duration.
  • PERT uses a weighted mean (), not a simple average of the three times.
  • **EOQ uses annual demand and per-unit holding cost ** — mixing monthly and annual figures is the usual error.

📚 Standard references

  • Project Planning and Control with PERT and CPMB.C. Punmia & K.K. Khandelwal
  • Construction Engineering and ManagementS. Seetharaman
PART 2

Progressive 3-Tier Question Suite

Q1BASIC1 Mark · NAT
Annual demand units, ordering cost , holding cost /unit/yr. The EOQ is _____ units.
Q2MEDIUM2 Marks · NAT
For an activity , , days, the PERT expected time is _____ days.
Q3HARD2 Marks · MCQ
On a CPM network, the critical path is the path with: